eglinton-crosstown tunneling comes to boring end

by:Gewinn     2019-09-09
After a long underground journey, Toronto\'s most popular tunnel rig
Don and Humber
Arrive at Yongji Street.
Send out finish 10-
Kilometers of LRT tunnel.
During the 3,300 m trip, Don and Humber installed 26,178 prefabricated concrete tunnel sections.
Dennis and Lea completed the tunnel excavation on the west side of the Crosstown Line in May.
LRT is expected to be operational in September 2021, 10 years after the start of construction.
Light rail car Press 2031-
Built by Bombardier-
It is expected that around 500 passengers will be transported per hour during peak travel times.
Once it\'s full
It is predicted that LRT will support up to 60 cents of travel faster than the existing bus service.
Construction is underway at three crosstown stations.
Kelsdale, Ryder and Avenue-
Preliminary demolition work is under way at all stations.
The new light rail line will have a total of 25 stations and stations along Eglinton Ave. —
Between Weston Road.
Kennedy Station-
54 bus lines, 3 TTC transfer stations and bus lines are connected.
The Ontario government has invested $5.
3 billion, the largest transportation project in the city for a generation.